Site | Date | Author | Summary |
Hill Slough |
(348) 2021-12-14 09:55:00 |
Daphne Szutu |
Swapped 7500 for calibration, changed eddy clock +1min, deployed new conductivity + water level sensor, 7700 optics desiccant needs to be swapped
|
Hill Slough |
(336) 2021-12-02 14:30:00 |
Joe Verfaillie |
High tide, replaced MiniDot.
|
Hill Slough |
(335) 2021-12-01 16:45:00 |
Daphne Szutu |
Regular data collection/cleaning, sunset, calibrated 7700, miniDOT was out of batteries
|
Hill Slough |
(322) 2021-11-18 08:30:00 |
Daphne Szutu |
Regular data collection/cleaning, close to low tide, dew on sensors, 7700 thermocouple broken--fixed, changed eddy clock +2min
|
Hill Slough |
(309) 2021-11-05 00:00:00 |
Daphne Szutu |
Breaches complete
|
Hill Slough |
(308) 2021-11-04 09:45:00 |
Joe Verfaillie |
Lowish tide, excavators still working on breach I think, tested tipping bucket, added MiniDot, added Eos CO2 probe, 7700 thermocouple broken, WD-40'd the locks, found some biofilms.
|
Hill Slough |
(299) 2021-10-26 09:30:00 |
Joe Verfaillie |
High tide - knee deep water at the tower, FD under water but seemed ok - removed, Well pipe floating - reinstalled, tested tipping bucket
|
Hill Slough |
(279) 2021-10-06 17:45:00 |
Joe Verfaillie |
First visit since levee breech - less than impressive, ditch full and some standing water far upwind. FD data not collected.
|
Hill Slough |
(278) 2021-10-05 08:00:00 |
Daphne Szutu |
First levee breach
|
Hill Slough |
(266) 2021-09-23 07:25:00 |
Daphne Szutu |
Regular data collection/cleaning, no water at the surface, swapped 7500 for calibration, changed eddy clock +1min, new gamecam from Ducks
|
Hill Slough |
(257) 2021-09-14 11:20:00 |
Daphne Szutu |
Brett called to say they will start slowly flooding
|
Hill Slough |
(246) 2021-09-03 09:00:00 |
Daphne Szutu |
Regular data collection/cleaning, barbed wire fence up, changed eddy clock +1min
|
Hill Slough |
(237) 2021-08-25 09:30:00 |
Daphne Szutu |
Fixed thermocouples, swapped dfPAR sensor, changed eddy clock +3min
|
Hill Slough |
(229) 2021-08-17 07:20:00 |
Daphne Szutu |
Regular data collection/cleaning, hazy skies, fixed TC1 and TC6 but more thermocouples need to be checked
|
Hill Slough |
(216) 2021-08-04 07:40:00 |
Daphne Szutu |
Regular data collection/cleaning, very windy and cold, new staff gauge with imperial units
|
Hill Slough |
(201) 2021-07-20 08:10:00 |
Joe Verfaillie |
Regular data collection/cleaning. Soil cores, RTK measurements and vegetation plots
|
Hill Slough |
(189) 2021-07-08 08:00:00 |
Ariane Arias-Ortiz |
Soil core collection (day 2)
|
Hill Slough |
(188) 2021-07-07 09:00:00 |
Ariane Arias-Ortiz |
Regular data collection/cleaning, soil cores (day 1)
|
Hill Slough |
(173) 2021-06-22 10:20:00 |
Daphne Szutu |
Regular data collection/cleaning, windy, spectral, removed rad cal kit
|
Hill Slough |
(167) 2021-06-16 14:00:00 |
Joe Verfaillie |
Set pi-cams locale and time, checked on cal kit, moved cal PAR from incoming to outgoing, checked on TC1 - still needs love
|
Hill Slough |
(160) 2021-06-09 17:30:00 |
Daphne Szutu |
Regular data collection/cleaning, super duper windy, measured sonic/eddy orientation, swapped 7500 for calibration, installed rad cal kit, changed eddy clock +1min
|
Hill Slough |
(146) 2021-05-26 10:00:00 |
Daphne Szutu |
Regular data collection/cleaning, calibrated 7700, took some spectral measurements, changed sonic heading
|
Hill Slough |
(133) 2021-05-13 09:45:00 |
Daphne Szutu |
Regular data collection/cleaning, super windy, road construction, front gate lock missing
|
Hill Slough |
(117) 2021-04-27 09:55:00 |
Daphne Szutu |
Regular data collection/cleaning, windy day, road construction on Grizzly Island Road, added RSB diffuse PAR sensor
|
Hill Slough |
(105) 2021-04-15 09:45:00 |
Daphne Szutu |
Regular data collection/cleaning, fresh green pickleweed growth
|
Hill Slough |
(89) 2021-03-30 09:15:00 |
Daphne Szutu |
Regular data collection/cleaning, windy day, all looks ok, wasps in met box
|
Hill Slough |
(84) 2021-03-25 09:00:00 |
Joe Verfaillie |
Working trip, new power line, 4-way net rad, FD chamber, soil cores, bolts, cleaning, tightening, measured sensor locations
|
Hill Slough |
(75) 2021-03-16 09:20:00 |
Daphne Szutu |
First site visit after setup, added precip bucket, fixed RH mux port, adjusted camera view, uploaded new config file for 7500
|
Hill Slough |
(70) 2021-03-11 09:30:00 |
Daphne Szutu |
Installed flux/met/rad sensors, Installed batteries, Ran temporary power line, Added chain link fencing to platform floors, Replaced broken solar panel
|
Hill Slough |
(61) 2021-03-02 07:50:00 |
Joe Verfaillie |
Entrance gate in poor place, dimensions of platforms
|
Hill Slough |
(57) 2021-02-26 14:40:00 |
Joe Verfaillie |
Initial set up of infrastructure, boardwalks complete, fencing done except entrance gate at beginning of boardwalk, broke one solar panel.
|
Hill Slough |
(34) 2021-02-03 13:00:00 |
Joe Verfaillie |
Met with contractors to confirm boardwalk plans - no major changes - ETA two weeks
|